● Construction of the Chupaderos Stream at Lazaro Cardenas Avenue, in Monterrey, N.L. from the Puerto Mexico street until connecting with the channel that passes under the Bridge that is located on Garza Sada Avenue. It includes the construction of circular ducts of reinforced concrete in interior diameters of 3.00, 2.80 and 1.80 meters, excavations, fillers and replacement of pavement. This work was contracted with the Municipal Administration of Monterrey, N.L.
● Sub Collector with pipe of 10” of diameter for the Residential Division Regio Parque Industrial, in Apodaca, N.L.
● Sub Collector with pipe of reinforced concrete of 18”, 24” and 30” of diameter in the Monterrey IV Project:
- Lermas Sub
collector. First Stage.
- Lermas Sub collector. Second Stage.
- Valle Hermoso Sub collector.
- Central of load Sub collector.